Time to service

 15.1. The HPC should complete all Customer Contracts within reasonable time called “time to serve” (the period from implementation of a Customer Contract till the time the scheduled work starts) is defined by the Program, based on the time of year, as: 

  • 4 weeks during May, June, July, and August
  • 5 weeks during March, April, September, and October 
  • 6 weeks during November, December, January, and February 

15.2. The HPC should complete all Assessment Work within a reasonable time called “time to serve” (the period from customer intake till the time the Assessment work starts) is defined by the Program, based on the time of year, as: 

  • 10 days during March, April, May, June, July, and August 
  • 15 days during January, February, September October November, and December

15.3. Abode can put exceptions for a time to serve extensions by Customer request.

Related Articles

Need Support?

Can't find the answer you're looking for?
Contact Support