Determine the duct sealing man-hours will base on the linear footage of current ridged ductwork and prevailing duct insulation.

  • 4 Man Hrs. (un-insulated rigid ducts less than 200 liner feet.)
  • 6 Man Hrs. (un-insulated rigid ducts greater than 200 liner feet.)
  • 8 Man Hrs. (insulated rigid ducts less than 200 liner feet.)
  • 12 Man Hrs. (insulated rigid ducts greater than 200 liner feet.)